Commercial Excavating Projects
Commercial Excavating Projects
J.S. Paris Excavating, Inc. has completed excavating projects for large industrial site development, distribution warehouses, and energy market expansions projects. We pride ourselves on exceeding our customer’s expectations by meeting deadlines and difficult requirements, despite inclement weather and aggressive scheduling. We are proud to have played a role in some of the most challenging building projects in Northeastern Ohio and Western Pennsylvania.
What we offer:
– Site excavation & grading
– Underground utilities – water, sanitary, storm
– Building pad
– Earthwork with storm water retention systems
– Road, driveway, and parking lot construction
– Demolition
Superior Beverage
Geis Companies
– Complete site development of 700,000 sf world headquarters
– 320K cy of earthwork
– 9,314 lf of 12″ water/fire line installation
– 5,960 lf of storm sewer installation ranging from 12″-72″
Arhaus World Headquarters
Premier Development
– Complete site development of 750,000 sf world headquarters
– 250K of earthwork
– 7,980 lf of 12″ water/fire line installation
– 4,320 lf of storm sewer installation ranging from 12″-60″
Old Rt. 8 Water Line
Boston Heights, Ohio
– Installation of 2,868 lf of 16″ water main and services along Old Rt. 8
RAMCO
Geis Companies
– Complete site development of 200,000 sf world headquarters
– 120K cy of earthwork
– 2,114 lf of 8″ water/fire line installation
– 1,160 lf of storm sewer installation ranging from 12″-36″
Hopedale Phase 3 Expansion
MarkWest
– 60,000 cy Embankment Construction
– 2,600 cy Rock Toe Key
– 1,600′ Storm Drainage
Riddell Helmet
Peak Construction
– Complete site development
– 350,000 sf Building Pad
– 52,000 cy Cut & Fill
– 7,000′ Storm Sewer
– 2,200′ Sanitary Sewer
– 4,400′ Waterline
Rite Aid Pharmacy
J T Butler LLC
– Complete Site Development
– Import 120,000 cy Fill Material
– Storm Sewer
– Sanitary Sewer
– Water Line
McMaster Carr Warehouse
Peak Construction
– Complete Site Development
– 402,000 sf Building Pad
– 38,000 cy Topsoil Strip
– 82,000 cy Cut & Fill
– 6,000′ Storm Sewer
– 4,300′ Water Line
Shell Distribution Warehouse
ARCO National Construction
– Complete Site Development
– 507,000 sf Building Pad
– 15,000 cy Topsoil Strip
– 92,000 cy Cut & Fill
– 5,200′ Storm Sewer
– 6,400′ Water Line
Project Chippewa Distribution
Geis Companies
– Complete Site Development
– 900,000 sf Building Pad
– 550,000 cy Cut & Fill
– 9,300′ Storm Sewer
– 9,600′ Water Line
Hopedale Phase 4 Expansion
Gas Processing Plant
MarkWest Energy Partners
– 200,000 cy Excavation
– 4,700′ Storm Sewer Installation
– Extensive Cement Stabilization
– Waterline & Hydrant Improvements
Project Rock & Roll
Geis Companies
– Complete Site Development
– 700,000 sf Distribution Warehouse
– 330,000 cy Cut & Fill
– 80,000 cy Top Soil Strip
– 7,000′ Storm Sewer
– 6,400′ Water Line
Blue Scope
Geis Companies
– Complete Site Development
– 434,000 sf Building Pad
– 165,000 cy Cut & Fill
– 3,500′ Storm Sewer
– 6,000′ Water Line
Innovation Ridge Office Complex
Al Neyer
– 30,000 sf Office Building Pad